<v Sam Kem>Hello, and welcome to the Economic and Market Watch podcast for the week of November 9, 2026. This is Sam Kem of CFC. Today, I am joined again by my coworker, Chris Whittle, CFC's energy and data analyst. Welcome back, Chris.

00:00:17.895 --> 00:00:20.055
<v Chris Whittle>Thanks, Sam. Great to be here as always.

00:00:20.295 --> 00:00:39.530
<v Sam Kem>Chris and I recently coauthored an issue brief titled The Grid Price Index: Measuring Cost Changes for Electric Cooperatives. We introduced the Grid Price Index or GPI in a previous episode where I explained what the index measures and how it was developed. So we're not going to repeat all of that today.

00:00:39.930 --> 00:00:54.425
Instead, we want to step back and talk about the larger story behind the index. What has changed in the electric equipment supply chain? Why so many costs remain elevated? And what coops can do to manage the risk?

00:00:55.000 --> 00:01:20.335
The theme running through the issue brief is that the economy and the electric utility industry in particular may now be operating with a structurally higher cost base. Chris, let's begin with one of the apparent contradictions in the current supply chain environment. Lead times for many products have improved considerably, but prices remain very high.

00:01:20.895 --> 00:01:23.535
How do we reconcile those two developments?

00:01:24.080 --> 00:01:53.335
<v Chris Whittle>I think the first step is to separate availability from affordability. During the worst of the pandemic disruption, the immediate problem was whether cooperatives could obtain any equipment at all. Lead times for transformers and other products stretched dramatically. Transportation networks were congested, manufacturers struggled with labor and material shortages, and many utilities had to place orders much further in advance. Those conditions have improved for many products.

00:01:53.940 --> 00:02:25.590
Some distribution transformer lead times, for example, have moved much closer to their pre-pandemic range. But improved availability does not mean that the industry's cost structure has returned to its pre-pandemic level. Manufacturers are paying more for labor, metals, energy, financing and transportation. They have also invested in additional production capacity and supply chain resilience. Those costs become embedded in the prices of finished equipment.

00:02:25.750 --> 00:02:39.785
<v Sam Kem>A construction budget developed using pre-pandemic assumptions simply does not purchase the same amount of equipment today, and there's no single explanation for that. Different equipment categories have different cost structures.

00:02:40.345 --> 00:03:14.885
The experience of the last several years changed the way many companies think about the trade off between resilience and cost efficiency. Manufacturers are more willing to invest in additional capacity before their existing facilities are completely full. Distributors are carrying more inventory. Utilities are placing orders earlier, qualifying alternative suppliers, and developing longer term agreements. Each of those decisions improves resilience, but each also carries a cost.

00:03:15.365 --> 00:03:35.415
<v Chris Whittle>Exactly. Inventory ties up working capital and requires additional warehouse space. Longer term contracts can improve supply certainty, but they also may include price escalation provisions. Developing alternative equipment specifications requires time from engineers and operations staff.

00:03:35.495 --> 00:04:09.855
<v Sam Kem>And that point came through clearly in the interviews we conducted for our research. At the manufacturing level, companies are investing in automation, more sophisticated machinery, and additional production capacity. That is encouraging because it can eventually improve equipment availability. But highly specialized manufacturing systems can take a year longer to order, install, and bring into production. A manufacturer cannot simply decide on Monday to produce significantly more transformers by Friday.

00:04:10.550 --> 00:04:40.670
<v Chris Whittle>And even after installing the equipment, the manufacturers still need skilled workers to operate and maintain it. Labor is one of the most persistent constraints in the industrial economy today. Manufacturers need machinists, technicians, production workers, and service personnel. Retirements are also removing experienced workers whose productivity and knowledge can be very difficult to replace. Automation can help address those shortages, but the initial investment can be expensive.

00:04:41.150 --> 00:04:46.110
Again, the solution to one risk can add to the industry's cost structure.

00:04:46.510 --> 00:05:02.085
<v Sam Kem>And then in the middle of the supply chain, distributors are serving as a kind of shock absorber. They maintain relationships with manufacturers, allocate equipment among utilities, and carry inventory so that critical products are available when members need them.

00:05:02.645 --> 00:05:32.905
When we spoke with the CEO of Resco, a supply co-op, he told us that Resco now carries roughly 25% to 30% more inventory in real terms than it did before COVID-19. It has also expanded its warehouse capacity. That approach helps protect members from supply disruptions. But with equipment prices so much higher, maintaining the same physical inventory requires significantly more capital.

00:05:33.960 --> 00:06:10.510
<v Chris Whittle>And at the electric-cooperative level, procurement has shifted from a largely tactical function towards a much more strategic one. Before the pandemic, a cooperative might wait for a commercial member to request service, then order the necessary equipment. Today, some equipment must be forecast and reserved months or even years in advance. When we spoke with Connexus Energy, they described reserving manufacturing slots for certain substation transformers needed in 2029 or 2030, even before they knew precisely where every unit would need to be deployed.

00:06:10.590 --> 00:06:31.295
<v Sam Kem>And that creates a difficult balancing problem. If a co-op orders too little, a shortage can delay a construction a new member connection, or reliability improvement. If it orders too much or orders the wrong specifications, it may tie up capital and equipment that sits unused.

00:06:31.295 --> 00:06:58.795
<v Chris Whittle>That's exactly right. Demand is also changing. Electrification, data centers, industrial projects, and the replacement of aging infrastructure can all alter the type and size of equipment a cooperative needs. Planning earlier reduces one type of risk, but it increases exposure to forecasting error. That makes coordination among procurement, engineering, finance, and operations increasingly important.

00:06:58.795 --> 00:07:06.900
<v Sam Kem>So how should co-ops respond? We obviously cannot eliminate commodity volatility, geopolitical risk, or manufacturing constraints.

00:07:07.140 --> 00:07:10.980
<v Chris Whittle>No, but cooperatives can make those risks more manageable.

00:07:11.620 --> 00:07:28.195
First, they can extend their procurement and capital planning horizons. That does not mean placing every order years in advance, it means identifying which equipment is most critical, which products have the longest lead times, and which projects are least able to tolerate delays.

00:07:29.030 --> 00:07:41.910
Second, they can strengthen supplier relationships and maintain secondary or tertiary sources where practical. Relationships with neighboring cooperatives can also be valuable during an emergency.

00:07:42.845 --> 00:07:59.740
Third, cooperatives can evaluate where equipment specifications might be made more flexible. If engineers can qualify reasonable alternatives before a shortage occurs, the cooperative has more options when a particular manufacturer or product becomes constrained.

00:08:00.380 --> 00:08:16.375
And finally, cooperatives should consider inventory and liquidity together. More inventory can improve reliability, but it also ties up capital. The right level will vary by cooperative, equipment category, and tolerance for operational risk.

00:08:16.855 --> 00:08:45.035
<v Sam Kem>I would also add that budgeting should include scenarios rather than relying on a single inflation assumption. A co-op could consider a baseline equipment-cost scenario, a higher equipment-price scenario, and a disruption scenario involving longer lead times or tariffs. The purpose is not to predict every possible event, but to understand how much flexibility exists in the capital plan if conditions change.

00:08:45.515 --> 00:09:11.745
The GPI can help provide a baseline for that process. It allows co-ops to compare the movement in their own equipment costs with broader industry trends and to see whether pressure is concentrated in a few categories or spread throughout the equipment basket. But the GPI should not be treated as a precise forecast or as a replacement for quotes from suppliers.

00:09:12.145 --> 00:09:40.235
<v Chris Whittle>Right. But it does provide useful market intelligence. It's essentially a benchmark that gives co-ops another perspective. Over time, as the GPI develops a longer history, it should become increasingly useful for identifying trends, evaluating budgets, and communicating cost pressures to boards of directors and members as well. It can also help distinguish between a temporary movement in one commodity and a broader increase in the cost of building out the grid.

00:09:40.475 --> 00:09:49.960
<v Sam Kem>If we pull all of this together, the key lesson is that today's higher equipment prices are not simply the result of one extraordinary pandemic shock.

00:09:50.200 --> 00:10:17.995
<v Chris Whittle>The grid is undergoing a major investment cycle. Utilities are replacing aging infrastructure, strengthening reliability and resilience, and preparing for new sources of electricity demand. Manufacturers and suppliers are also investing to increase capacity and make their operations less vulnerable to future disruptions. These investments are necessary, but they require more equipment, more labor, more inventory and more capital.

00:10:18.690 --> 00:10:31.170
<v Sam Kem>We are effectively paying an insurance premium for greater resilience. The goal is to determine where redundancy provides real operational value and where additional cost is not justified.

00:10:31.815 --> 00:10:41.895
<v Chris Whittle>And the balance will look different for each co-op, but making it requires better information, longer planning horizons, and stronger coordination across the whole industry.

00:10:42.295 --> 00:11:10.475
<v Sam Kem>Our issue brief, "The Grid Price Index: Measuring Cost Changes for Electric Cooperatives," examines these issues in greater detail. It includes the latest GPI analysis as well as perspectives from manufacturing, equipment supply co-ops, and electric co-ops putting new procurement strategies into practice. And trust me, you don't want to miss out on this one. You can read and download the issue brief in the link provided in the show notes.

00:11:11.035 --> 00:11:12.955
And Chris, thanks for joining me today.

00:11:13.650 --> 00:11:16.370
<v Chris Whittle>My pleasure, Sam. I really enjoyed the conversation.

00:11:16.850 --> 00:11:23.650
<v Sam Kem>That's it for today. Thank you for listening. Be sure to download the Economic and Market Watch intelligence brief and dashboard. Talk to you soon.